Philosophy Politics Economics |
KLIA 2: Delay and More Delays? Posted: 30 Dec 2011 10:33 PM PST When will KLIA2 - the new "low-cost terminal" actually get completed? 1. September 2011 Deputy Transport Minister Datuk Abdul Rahim Bakri, who also attended the press conference, said the tender for the construction of the new LCCT will be called as soon as the design is completed. The new LCCT is expected to be completed by September 2011. The terminal, estimated to cost RM2 billion, will be built about 2km away from KLIA. ~ 30/10/2009 Business Times The building of a new Low Cost Carrier Terminal (LCCT) will be completed by the end of 2011 although its construction faced some delay, said Deputy Transport Minister Datuk Abdul Rahim Bakri. "The project's progress should be 15.5 per cent but right now it is 13.5 per cent. Based on the current status the delay is two per cent or 18 days," he said. ~ 17/11/2009 Bernama 2. Early 2012 The new low-cost carrier terminal (LCCT) is expected to be ready by late 2011 or early 2012, said Malaysia Airports Holdings Bhd's (MAHB) managing director, Tan Sri Bashir Ahmad. Earlier, it was expected to be ready by September 2011. ~ 1/9/2010 Bernama 3. April 2012 Kumpulan UEM Bhd. dan Bina Puri Holdings Bhd , yang bertindak sebagai kontraktor utama bagi terminal baru itu memberi jaminan projek itu akan disiapkan tepat pada masanya … ''Kami berupaya menepati tempoh pembinaan yang ditetapkan dan penyerahan KLIA2 akan dibuat pada akhir tempoh 20 bulan (April 2012) seperti yang ditetapkan kerana kami memiliki sumber, kepakaran dan pengalaman,'' janji Pengarah Urusan Kumpulan UEM, Datuk Izzaddin Idris. ~ 1/9/2010 Utusan Malaysia 4. October 2012 Semua syarikat penerbangan tambang murah akan berpindah ke terminal penerbangan tambang murah tetap baru, KLIA2, yang dijadualkan siap pada bulan Oktober 2012, kata Menteri Pengangkutan, Datuk Seri Kong Cho Ha. ~ 25/1/2011 Kosmo 5. April 2013 SEPANG: The new low-cost carrier terminal, expected to be operational by April 2013, will cost Malaysia Airports Holdings Bhd (MAHB) between RM3.6 billion and RM3.9 billion, and it will come with aerobridges. ~30/11/2011 Business Times Will that be the last and final delay? |
You are subscribed to email updates from Philosophy Politics Economics To stop receiving these emails, you may unsubscribe now. | Email delivery powered by Google |
Google Inc., 20 West Kinzie, Chicago IL USA 60610 |
Tiada ulasan:
Catat Ulasan